Last week, I was on a technical meeting about natural gas counters of Kazeroon combined cycle power plant. The meeting was held on Mapna (Iran Power Plant Projects Management) company. I was there as a consultant and tried to persuade the contractor to buy local counters, but they didn't want to do that. Finally the client(Iran Power Development Company) stated that I am right and according to the contract, contractor should implement local counters but according to value engineering they can neglect the counters!!!

Have you ever heard about value engineering? I think it is discussed in industrial engineering, but I'm sure that its meaning has been changed in Iran's industrial projects. It is funny and also painful. What's your idea